Emerson Process Management 2400S Pacemaker User Manual


 
Configuration and Use Manual 109
Measurement Performance
Measurement Performance DefaultsTroubleshootingCompensation
10.3.5 Setting up automatic or remote execution of the meter verification test
Note: Requires Smart Meter Verification. Scheduling is not available with the original version of the
meter verification application.
There are three ways to execute a Smart Meter Verification test automatically:
Define it as an event action
Set up a one-time automatic execution
Set up a recurring execution
You can use these methods in any combination. For example, you can specify that a Smart Meter
Verification test will be executed three hours from now, every 24 hours starting now, and every time a
specific discrete event occurs.
To define meter verification as an event action, see Section 8.6.
To set up a one-time automatic execution, set up a recurring execution, view the number of
hours until the next scheduled test, or delete a schedule:
- With ProLink II, click
Tools > Meter Verification > Schedule Meter Verification.
- With the display, see Figures 10-6 and 10-14.
- With the EDD, see Figure 10-15.
- With PROFIBUS bus parameters, see Figure 10-16.
Note the following:
If you are setting up a one-time automatic execution, specify the start time as a number of
hours from the present time. For example, if the present time is 2:00 and you specify 3.5 hours,
the test will be initiated at 5:30.
If you are setting up a recurring execution, specify the number of hours to elapse between
executions. The first test will be initiated when the specified number of hours has elapsed, and
testing will be repeated at the same interval until the schedule is deleted. For example, if the
present time is 2:00 and you specify 2 hours, the first test will be initiated at 4:00, the next at
6:00, and so on.
If you delete the schedule, both the one-time execution and the recurring execution settings are
deleted.