51
Reference Manual
00809-0100-4102, Rev AA
Section 3: Installation
May 2013
Installation
Drain/
Vent
Valve
Drain/
Vent
Valve
Equalize
(closed)
Process
Isolate
(open)
Isolate
(open)
H
L
In normal operation the two block
valves between the process and
instrument ports will be open and the
equalizing valve will be closed.
Drain/
Vent
Valve
Equalize
(closed)
Process
Isolate
(closed)
Isolate
(open)
H
L
1. To zero the 2051, close the
block valve to the low
pressure (downstream) side
of the transmitter first.
Drain/
Vent
Valve
Drain/
Vent
Valve
Drain/
Vent
Valve
Equalize
(open)
Process
Isolate
(closed)
Isolate
(open)
H
L
2. Open the center (equalize)
valve to equalize the pressure
on both sides of the
transmitter. The manifold
valves are now in the proper
configuration for zeroing the
transmitter.
Drain/
Vent
Valve
Drain/
Vent
Valve
Equalize
(closed)
Process
Isolate
(closed)
Isolate
(open)
H
L
3. After zeroing the transmitter,
close the equalizing valve.
Drain/
Vent
Valve
Drain/
Vent
Valve
Equalize
(closed)
Process
Isolate
(open)
Isolate
(open)
H
L
4. Open the block valve on the
low pressure side of the
transmitter to return the
transmitter to service.