3. Press the LAMP ON switch: the green LAMP ON indicator blinks, then stays lit.
4. Check the line currents. The line currents should conform to the values in Table
11.
5. Check RF detector and customer use interlocks as described in Chapter 5,
“Troubleshooting.”
Initial Startup Procedure, Multiple-Unit Systems
1. Turn POWER switches of all units to ON.
2. Press the LAMP OFF/RESET switch of the Master.
3. Press the LAMP ON switch of all slaves.
4. Press LAMP ON switch of the Master.
NOTE: Front panel controls take precedence over remote or master commands.
Master/Slave Operation
One master power supply can control up to five slave units. Review Chapter 2,
“Mechanical Installation” to understand the interconnections and programming
needed.
Operating the System
1. Turn POWER switches of all units to ON.
2. Press the LAMP OFF/RESET switch of the Master.
3. Press the LAMP ON switch of all slaves.
Table 11. P300M/P300MQ/P300MT Current Requirements
System Line
Voltage
Single Phase
Line Currents (A)
with K300M
Modular Blower
without K300M
Modular Blower
200 15 14.5
208 14 13.5
220 14 13
230 13.5 13
240 13.5 12