Fusion F300SQ Light Therapy Device User Manual


 
Installation, Operation, and Maintenance Manual # 509252 Rev R 31
Chapter 2. Mechanical Installation
Mechanical Installation Checklist
Before operating the ultraviolet lamp system for the first time, be sure the following
procedures have been completed.
This chapter describes the physical installation of the F300S/F300SQ Fusion UV
Lamp System. Directions regarding mounting and shielding of the system are
somewhat general because they will vary depending upon the details of each
individual installation.
Unpacking and Inspection
This Fusion UV lamp system has been thoroughly tested inspected, and packed prior
to shipment. Before unpacking, examine all shipping containers for damage. After
unpacking, examine the equipment for damage. Any damage should be reported
immediately to the shipper and to Fusion UV Systems Incorporated. A delay of more
than 10 days may invalidate future claims for damages.
CAUTION: Irradiators are particularly vulnerable to dust, dirt, metal
chips, and RF screen damage. They are shipped with a protective
covering over the screen. The covering should not be removed until just
prior to installation.
When unpacking, identify and compare each item with the packing list enclosed.
Remember to examine each component for damage. Appendix E, “Replacement Parts”
details the items included with the system which will be required to complete the
installation.
Table 3. Mechanical Installation Checklist
Item Chapter
Review safety procedures Chapter 1, “Safety”
Light shields in place “UV Light Shielding” on page 34
RF detector positioned correctly “RF Detector Mounting” on page 35
Fan connection for exhaust of light shield “Remote Blowers” on page 36
RF screen and lamp bulb inspected Introduction, page 11