Welch Allyn Medical Diagnostic Equipment 300 Series Pacemaker User Manual


 
3
9
Functional verification
Functional verification overview
This section describes the procedure for a complete functional test to support
recommended preventive-maintenance schedules.
The verification includes tests for a monitor configured with the printer, temperature, and
SpO
2
options. Perform only the tests applicable to the actual configuration.
A checklist of the functional tests is provided on “Checklist and test results report form”
on page 31. It is recommended that you print a copy of the checklist each time you
perform the functional verification procedure, so that you can record and save the test
results. If the monitor ever requires service, the records of test results can often facilitate
troubleshooting.
Functional verification does not require opening the monitor case.
Equipment required
This equipment is required for functional verification of a fully configured monitor.
Commercially available general-purpose/medical test equipment
Item Manufacturer part number/specification
Power supply Variable, 0-8 VDC, 0.75 amperes (minimum), with voltage and current
indicators (for 1mA current measurement)
Digital pressure meter NetechDigimano 1000 or equivalent
AC withstand voltage (hi-pot) tester Associated Research 3605 or equivalent
SpO
2
functional tester (Nellcor, for testing
the monitor only)
Nellcor SRC-MAX
SpO
2
functional tester (Masimo, for testing
the monitor only)
Masimo Tester REF 1593
SpO
2
extension cable (required for SRC-
MAX)
Nellcor DEC-8
SpO
2
simulator (for testing the monitor and
the SpO
2
sensor)
Fluke (Biotek) Index2 XL/XLFE or equivalent
Syringe, 60 mL, Slip tip, Luer BD (Becton, Dickinson) 309654 or equivalent
Hi-pot cable connectors See “Test connections” on page 29.
Timer (to display elapsed time, in seconds)