Emerson 3414 Oxygen Equipment User Manual


 
Daniel 3410 Series Ultrasonic Gas Flow Meter Installation Manual Section 3: Electrical installation
3-9000-759 Rev D June 2014
Startup for systems using explosion-proof conduit 49
6. Set or configure the meter operating parameters using Daniel MeterLink. For additional
installation information refer to the system wiring diagram (see Appendix A), Daniel
MeterLink Software for Gas and Liquid Ultrasonic Meters Quick Start Manual
(P/N 3-9000-763) and use the Daniel MeterLink Field Setup Wizard to complete the
configuration.
7. Verify the field connections are working correctly. Allow the system to run for the time
specified by the customer (usually one week) and an electrician has fully tested the
connections. After the Acceptance Test is witnessed and approved, seal the conduit.
8. Power down the system and apply the sealing compound to the conduit and allow to
set in accordance with manufacturer specifications.
9. If required, install the security latches and wire seals on the Transmitter Electronics
Enclosure end caps (see Section 3.7 and Figure 3-11).
10. If required, install the wire seals through the socket head bolts on the Base Enclosure
(see Section 3.7, Figure 3-12 and Figure 3-13).
11. Re-apply electrical power to the system.