With new rope installed on the drum as described in paragraph
5-9c single reeved above, proceed with rereeving following
steps below:
(1) Pass other end of rope thru bottom opening of hoist,
between floating limit rod and motor, and attach rope to cast
dead end anchor fitting. A slot is located at top of fitting to
accept cable. Reinstall bolt and lockwasher in end of anchor
fitting to lock rope compression fitting in place.
(2) Grasp loop, formed after installing end anchor, and
place bottom block sheave in loop. Lower sheave into bottom
block and insert sheave pin. Replace key plates and bolts
holding sheave pin in place.
(3) Replace sheave guard. Make certain rope is not
twisted. Should the two parts of rope tend to wind around
each other, remove cable from anchor slot and untwist cable.
Reattach the cable anchor.
(4) Lubricate cable per paragraph 4-3.
(5) Remove key plates or snap rings from upper block
sheave(s) and slide out upper block sheave pins, releasing
upper block sheaves. Remove wire rope from sheaves.
(6) Make certain all personnel are clear of hoist and
operate hoist
ââ
ââ
â to completely unwind all wire rope from
drum. Stop hoist so drum anchor slot(s) is accessible. Remove
live rope and socket(s) from drum.
(7) TURN OFF POWER TO HOIST.
(8) Remove the bolt and lockwasher in the end of the
rope anchor fitting. Remove rope from slot in top of anchor.
c. Installing new rope.
Winding rope on rope drums with power can be
hazardous. Keep hands safe distance from drum, wear
gloves and use extreme care when handling rope.
WARNING
SINGLE REEVED HOISTS
Stretch new cable on floor in one continuous length. Make
certain there is no twist in rope.
(1) Place one end of rope in rope drum anchor slot. Be
sure end fitting is properly seated.
(2) With all personnel clear of hoist — TURN ON
POWER.
(3) Operate hoist
áá
áá
á, guiding new rope into drum grooves
with gloved hand, until the following lengths remain unwound:
(a) 2 part single reeved — about 14'-0".
(b) 4 part single reeved — about 28'-0".
(c) 6 part single reeved — about 42'-0".
(4) Proceed with reeving as described in appropriate
paragraph below and the reeving diagram for your hoist.
DOUBLE REEVED HOISTS
Stretch new cable on floor in one continuous length. Make
certain there are no twists in rope.
(1) Pull far end of rope toward end of rope nearest hoist,
until both ends are even and a loop is formed. Place fittings
on both ends of rope in anchor slots on rope drum. Be sure
end fittings are properly seated.
(2) With all personnel clear of hoist — TURN ON
POWER.
(3) Operate hoist
áá
áá
á guiding rope into grooves at both
ends of drum, until the distance from the drum to the loop is
— about 28' for 2 part double reeved.
(4) Proceed with reeving as described in appropriate
paragraph below and the reeving diagram for your hoist.
d. Reeving — 2 part single.
See Figure 5-12 for diagram.
See Figure 9-11 for block parts.
Figure 5-12. Hoist Reeving — Two Part Single.
e.
Reeving — 4 part single.
See Figure 5-14 for diagram.
See Figure 9-13 for block parts.
With new rope installed on the drum as described in
paragraph 5-9c single reeved above, proceed with rereeving
following steps below:
(1) Grasp the cable near the middle (about 14'-0") of
the unwound end and form a loop. Place upper sheave in
this loop. Slide upper sheave with cable into sheave pocket.
(2) Insert sheave pin into sheave. Replace key plates
and bolts to hold sheave pin in place.