800 Series Operator's Manual5Ć34
b. Press 2 Maintenance Tasks and press Enter.
The Maintenance Setup screen appears, as shown in Figure 5-19.
2. Enter the start date for recording the maintenance tasks.
Tasks become due on midnight of the scheduled date. For example, weekly
tasks are due every 7 days after the start date, monthly tasks are due every
fourth week after the start date.
3. Take the appropriate action.
keep the existing
maintenance schedule
go to step 10.
change the frequency of a
maintenance task
go to step 4.
4. Select Edit Frequency.
5. Use the arrow keys to select a task.
6. Select
Select Frequency.
7. Use the arrow keys to select a frequency for the task.
8. Select
OK to change the frequency or select Cancel to return to the
Maintenance Schedule screen.
9. Repeat steps 5 through 8 to change the frequency of another task or go to step
10.
10. Press
Done to return to the Main menu screen.