2.7 Other Standard Installation Procedures
This section contains other procedures done at every installation after the RAN is mounted on a
wooden pole or concrete pad.
2.7.1 Installing a Solar Shield
Each RAN has a solar shield that mounts on top of the cabinet. Hardware for the solar shield can
be found in a bag fastened to the inside of the battery compartment. The hardware consists of
two 1/4 in. bolts, each with flat washer and sealing washer. Use the following procedure to
install the solar shield. Refer to Figure 31.
1. Remove the solar shield from its packaging.
2. Place a lock washer and flat washer and then the sealing washer on each 1/4 in. machine
bolt.
3. Using the key provided, open the RAN door.
Figure 31. Installing the Solar Shield