A SERVICE OF

logo

EQQZ125E EQQZ129I
EQQZ125E OPC/ESA CANNOT CONTINUE PROCESSING DUE TO FULL QUEUE:
QNAME
THE SUBSYSTEM IS
TERMINATING
Explanation: One of TME 10 OPC internal queues is full. The subsystem was cancelled by the task that added the
last element.
System action: The TME 10 OPC subsystem terminates.
Problem determination: Check the TME 10 OPC MLOG for EQQZ106W messages indicating which queue is full.
Check for other previous messages about the subtask processing the queue:
MGRQ Event manager
SUBQ Submit task
RTRQ Data router task
NCFQ NCF task
TME 10 OPC administrator response: Restart the TME 10 OPC subsystem. Verify that all subtasks start normally.
EQQZ126W THE SYSTEM WHERE THE OPC/ESA HOST IN THE XCF GROUP
XCFG
WAS RUNNING HAS
FAILED. A TAKEOVER BY THE STANDBY HOST
XCFSTB
MUST BE INITIATED BY THE
OPERATOR.
Explanation: The TME 10 OPC standby system has detected that the MVS image on which the TME 10 OPC host
is located is down.
System action: None.
User response: Restart MVS and the TME 10 OPC host, or use the MODIFY command to order the TME 10 OPC
standby system to perform a takeover of the controller functions.
EQQZ127W THE OPC/ESA HOST IN XCF GROUP
XCFG
HAS FAILED. A TAKEOVER BY THE STANDBY HOST
XCFSTB
MUST BE INITIATED BY THE OPERATOR.
Explanation: This TME 10 OPC standby system has detected that the TME 10 OPC host is not running.
System action: None.
User response: Restart the TME 10 OPC host, or use the MODIFY command to order the TME 10 OPC standby
system to perform a takeover.
EQQZ128I OPC/ESA ACTIVE IN STANDBY MODE
Explanation: This system has been fully initialized in standby mode.
System action: None.
System programmer response: None.
EQQZ129I TAKEOVER IN PROGRESS
Explanation: This system has started takeover processing.
System action: The system continues initialization as the new host.
System programmer response: None.
Chapter 33. EQQZnnn Messages 423