Page 40 of 77 SCW Series Central Chilling Stations
5-6 Determining Flow Rate
To determine flow:
1. Close the gauge cock leading to the pump suction side and
open the gauge cock leading to the pump discharge.
2. Start the pump and make note of the discharge pressure in
psi (kPa/bars).
3. Check the pump curve for the appropriate horsepower
pump at the discharge pressure psi.
4. Project this point down to find the flow in gpm (lpm).
5. Process pumps can be left wide open if running amps are
below full load amps.
5-7 Shutdown
1. Ready process and related equipment for shut down.
2. Donot turn off main power until chiller completes the shut-
down sequence (approximately 2 minutes).
3. Close the water make up valve.
4. If the system is to be drained, open the 2” drain valve.
Figure 4
SCW Series Standard Control Panel
Figure 5
SCW Series Advanced Control Panel
-Notes-