Smeg WO-01 Home Dialysis Equipment User Manual


 
- 35 -
Pressurizing and starting up the unit:
After all pipes have been connected, pressurise
the system gradually and check for leaks.
Turn the “Osmosis pump” switch to “I”. Check
that the following message displays:
In normal operation the value Rj varies during
osmosis-treated water production.
Wait 5-10 minutes, then continue by starting up
the delivery pump.
Osmosis pump switch
I M P O R T A N T !!!
Delivery pump startup (first startup)
Remove the red bleeder cap P (“Sfiato innesco”)
on the front (close to the pressure gauge,
labelled as such) .
To remove the cap, press the John Guest clip
and allow a bit of water to run into a container;
refit the cap P, and actuate the “Delivery pump”
switch.
FAILURE TO FOLLOW THIS PROCEDURE TO
THE LETTER CAN CAUSE SERIOUS
DAMAGE TO THE DELIVERY PUMP.
Delivery pump switch Cap “P”