5 - 1
5.1 Q Series Safety Relay Module
5.1.1 Start-up procedures
5
SETTINGS AND PROCEDURES BEFORE
OPERATION
CHAPTER 5 SETTINGS AND PROCEDURES BEFORE
OPERATION
This chapter explains settings and procedures before operating the safety relay module.
5.1 Q Series Safety Relay Module
5.1.1 Start-up procedures
Figure 5.1 shows start-up procedures for the Q series safety relay module.
Figure 5.1 Start-up procedures (1/2)
* 1: Refer to Section 5.3
Yes
No
Start
Set the extension module station
number and extension communication
terminating resistor setting switch.
*1
Connect the main module and an
extension module with a safety circuit
part extension cable.
*1
Mount a main module on the base unit
and install it to a control panel or
machine.
Connect an extension module?
Connect the monitor part (EA, EB,
EG, EP) with shielded cable.
Connect a safety part terminating
connector to the last module.
Set start-up mode with start-up input
mode setting switch.
(To next page)