Harmar Mobility CPL1000 Personal Lift User Manual


 
Preparing to Install the Lift
Final Site Inspection
Verify the surface the lift will mount to is smooth and level. This surface must be made from 3,500 psi
reinforced concrete with a minimum thickness of 4”.
Verify that there is enough space for the lifts foot print. Be sure to include space neccesary for platform.
Caution: Verify that the running clearance around the lift complies with
any codes for your area.
The horizontal gap between the edge of the platform and the upper landing must no less than 3/8”
and no greater than 3/4”.
The horizontal gap between the guard panel and any wall or barrier must be no less than 2” and
no greater than 3”.
Verify that sufficient head room exists above the lift. The lift will require 6’ 8” of clearance above
the platform floor when the lift is at the upper landing.
Warning: The area between the floor where the lift is mounted and the top
landing must be covered by a smooth vertical fascia. This is to to eliminate any pinch
points between the platform and landing.
Connecting to Electricity
The lift will require a 115 VAC 20 amp grounded electrical circuit.
Depending on local codes, this connection may need to be routed in electrical conduit and hard-wired.
Warning: Do not ride on the lift until it has been anchored in place.
Controller Harness Connections
5
HighVoltage
CircuitBreaker
(ACunitonly)
LowVoltage
CircuitBreaker
Platform
TravelingCable
PhoneJack
Connection
SafetyPan
Jumper
UpperLanding
Interlock
LowerLanding
Interlock
Upper&Lower
CallSends
Upper&Lower
LimitSwitches
BypassSwitches
(Strikesonly)