5. Mount the Blower Motor and Check Valve - Remote
NOTE: The blower motor must be mounted horizontally 1-1/2″ (38 mm) above the floor. Do not mount
the blower motor with the discharge pointing up.
NOTE: Refer to the ″Prepare the Blower (Remote Site)″ section for other requirements for the blower
motor relocation.
At the new blower motor location, install a 1-1/2″ (38 mm) high block (not supplied) to support the
blower motor.
Use the blower motor as a template to mark the location of the four mounting bolts or screws.
Drill four 1/8″ (3 mm) pilot holes for the blower motor mounting screws.
Install and support PVC or other 1-1/2″ rigid piping (not supplied) between the blower motor
location and the air harness.
Connect the new piping to the existing air harness without modifying the air harness. Align the new
pipe and secure the connection with PVC cement. Allow the PVC cement to cure according to the
manufacturer’s instructions.
Connect the check valve assembly to the new piping. Align the new pipe with the check valve
assembly and drill a hole for the existing mounting screw. Use silicone or equivalent sealant at the
connections and reuse the screw that was removed previously. Allow the sealant to cure according
to the manufacturer’s recommendations.
Position the motor on the support block. Reinstall the screw on the check valve.
Fasten the blower motor to the new support block with the mounting screws.
Check Valve
Screw
Screw
Blower Motor
Mounting Screws
1-1/2" Rigid Piping
(not supplied)
1-1/2" (38 mm) Min
Kohler Co. 9 1199249-2-A